TÜRKÇE
  Updated: 04/03/2022

Sorgun Wastewater Treatment Plant Project

 

 

GENERAL INFORMATION
 

Project title
 

Sorgun Wastewater Treatment Plant Project

Priority area
 

Water (infrastructure related activities) / Environment and Climate Action

Beneficiary

Sorgun Municipality

Co-Beneficiary
 

-

Duration

Wastewater Treatment Plant 20 months

December 2020 – August 2022

EU contribution (Euro)

8.024.0000

 

 

 

 

PROJECT SUMMARY

Brief description of the project and main objectives
 

Construction of wastewater treatment plant.

Improving the water quality of Eğriöz River via reducing pollution load caused by untreated wastewater discharge in the existing situation and contribute to improvement of public health.

Location

Sorgun (Yozgat)

Achievements / expected outputs

With the construction of the wastewater treatment plant, the needs of the region in terms of wastewater treatment services will be met until 2048.

 



Updated: 04/03/2022 / Hit: 2,034